Springvale Estate

Liftec Ltd

Hammersmith & Fulham

AES took responsibility for the entirety of scoping and delivering all building and electrical works required for this project.

The work included the following:

  • Attended pre-start meetings with Liftec project manager and council representative to scope works required
  • RAMS and programme of works produced and shared with relevant people
  • Hoardings and floor protection installed
  • Entrances removed and lintels raised
  • Apertures formed in preparation for new thresholds
  • Shaft and motor room spray-painted
  • Metal containment installed in the lift shaft
  • Electrical mains cable installed from intake room through the lift shaft into the motor room in preparation for the new power supply
  • Governor holes core drilled
  • Architraves back-poured using a fine concrete mix
  • Apertures cut and push-boxes installed
  • Hoardings removed
  • Rendered feature applied to every entrance
  • Thresholds made good
  • Decoration
  • New circuit energised
  • Motor room and lift pit floor degreased and painted with oil-based floor paint
  • Electrical installations inspected, tested and certificated

In completing the job handover, no snagging items were identified by Liftec Ltd.